Art3_Apple Valley_FY23_BikePed_McConnell Park Multi-Use Path_AppTDA Article 3 Grant Application: Bicycle & Pedestrian Project
Project Title McConnell Park Multi-Use Path
Priority if Submitting 2
Multiple Applications
Project Type Installation of new facility
Project Length 0.25 miles
Local Match Funding Measure I
Sources
Contact Name Julie Ryan
Agency Apple Valley
Contact Phone 760-240-7000
Contact Email jryan@applevalley.org
Project Need & Purpose
Clear project
description
Construct a new concrete multi-use path along Pahute Road leading from Navajo
Road to the newly constructed Captain Joseph McConnell Jr., USAF Park.
PUBLIC OUTREACH
Captain Joseph McConnell, Jr., USAF Park
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
October 10, 2020 October 10, 2020
November 2, 2020 November 2, 2020
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
January 27, 2021
February 3, 2021
PUBLIC OUTREACH
Captain Joseph McConnell, Jr., USAF Park
PHOTOGRAPHS OF EXISTING CONDITIONS
Captain Joseph McConnell, Jr., USAF Park
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
Pahute Road looking east Pahute Road looking west
Asphalt pathway condition Asphalt pathway condition
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
PHOTOGRAPHS OF EXISTING CONDITIONS
Captain Joseph McConnell, Jr., USAF Park
Asphalt pathway condition Asphalt pathway condition
Asphalt pathway condition Asphalt pathway condition
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
PHOTOGRAPHS OF EXISTING CONDITIONS
Captain Joseph McConnell, Jr., USAF Park
Asphalt pathway condition No pathway and non ADA Compliant
Asphalt pathway condition Pahute Road looking towards the future Captain Joseph
McConnell Jr., USAF Park
Town of Apple Valley
SBCTA Transportation Development Act (TDA) Article 3
Bicycle & Pedestrian Improvements
PHOTOGRAPHS OF EXISTING CONDITIONS
Captain Joseph McConnell, Jr., USAF Park
Pahute Road looking west Pahute Road looking towards the future Captain Joseph
McConnell Jr., USAF Park
Pahute Road looking west Pahute Road looking west
McConnell Park Multi-Use Path
Description Qty.Unit Unit Price Extended Amount
1 Grading 1 LS 25,000.00$ 25,000.00$
2 Demolition and Removal 1 LS 10,000.00$ 10,000.00$
3 8" concrete curb and gutter 1,100 LF 40.00$ 44,000.00$
4 4" concrete sidewalk 10,300 SF 7.00$ 72,100.00$
5 4" asphalt Concrete 24,022 SF 5.00$ 120,110.00$
6 Driveway Approach 4 EA 25,000.00$ 100,000.00$
7 Construction staking 1 LS 10,000.00$ 10,000.00$
8 Traffic striping and legend 1 LS 3,500.00$ 3,500.00$
9 Traffic control 1 LS 16,000.00$ 16,000.00$
Total 400,710.00$
15%80,142.00$
480,852.00$
TDA 240,426.00$
Match 240,426.00$
Engineer's Estimate
Source: USDOT's Transportation Disadvantaged Census Tracts tool
Project Limits
McConnell Park Multi-Use Path Project
7/3/2023
SCALE: NTS SHEET 1 OF 1
Disadvantaged Community Data
Town of Apple ValleySource: Census Reporter
New Asphalt Concrete Roadway
New drive approach New drive approach New drive approach New drive approach
New 10' Wide ADA Compliant
Concrete Pathway