CITY of CHINO
April 10, 2019
Cameron Brown
Senior Planner
San Bernardino County Transportation Authority
1170 W. 3rd Street, 2nd Floor
San Bernardino, CA 92410
cbrown@gosbcta.com
Subject: Chino 2013/14 TDA Article 3 Central Ave. Sidewalk Project — Request for
Extension of Funds
Dear Cameron,
SBCTA awarded TDA Article 3 funds to the City of Chino for the Central Avenue Sidewalk
Project. The projects were to be completed by December 31, 2018. The Project has
experienced delays mainly due to turn over in staffing in the Public Works Department in
the last couple of years. The City has hired additional staff and secured services of
consultants to complete this and other projects. The City is working expeditiously on
design of the Project and moving it forward. We hope to put the plans out to bid for
construction in July/August of 2019 and complete construction in early 2020.
This letter is to request an extension of two years to complete the Project by December
31, 2021.
7!el y,y,
Amer Jakher
Director of Public Works
City of Chino
13220 Central Avenue, Chino, California 91710