Art3_Adelanto_FY19_Transit_JohnathanChamberlaine_App (2)City of Adelanto TDA Art 3 - Project 2 Conceptual Phase Engineer's Estimate - May 2, 2019 Chamberlaine (Crippen) Way from Highway 395 to Jonathan Street Sidewalk and Ramp Scope No. Description Mobilization Traffic Control Erosion Control, BMPs Grading and Earthwork Construct curb & gutter Construct new curb ramp Remove PCC/AC Driveway Remove PCC Ramp Construct drive approach Construct sidewalk Quantity 1 1 1 1 1570 6 750 100 750 10750 Construction Sub-Total Contingency (15%) Construction Total Engineering, Admin & Legal Rounded Hardscape Total Unit LS LS LS LS LF EA SF SF SF SF Unit Cost 10000 2000 2000 2000 45 4000 6 6 10 8 Amount 10000 2000 2000 2000 70650 24000 4500 600 7500 86000 209250 31387.5 240637.5 41850 283000