Art3_RanchoCucamonga_FY19_Transit_5stops_App
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2017/2018 - FY 2018/2019
1. Bus Stop No.: 1
2. Project Title: Arrow Route Bus Pad, East of Malachite Ave.
3. Project Description (attach photos and more thorough description as appropriate):
Construct concrete bus pad between the curb and sidewalk. This project will
provide transit riders easier access to local businesses. It will improve access for
disabled riders by providing connection from the bus stop to the existing
sidewalk. The project will be constructed within the existing right of way.
4. Location: North side of Arrow Rte, East of Malachite Ave.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 3,735
6. Non-TDA Article 3 Project Matching Funds: $ 747
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 2,988
8. Location Characteristics:
85 Bus Routes Serving Location
34 Number of Daily Buses Serving Location
19 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Arrow Route from Hellman Ave. to Center Ave. (Table 5.89)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by industrial complexes and single family units. Route 85
provides service to or stops within the proximity of: Chino-Upland-Rancho
Cucamonga Civic Center, Chino-Montclair-Chaffey Transit Center, Montclair
Plaza, San Bernardino County Offices, San Antonio Hospital, Kaiser Clinic,
Chino-Montclair-Los Osos High School and Chaffey College.
North side of Arrow Rte., East of Malachite Ave., looking west.
North side of Arrow Rte., East of Malachite Ave., looking east.
Bus Stop 1
Arrow Rte. (N/S & West Bound), East of Malachite Ave.
Item No. Item Quantity Unit Unit Cost Total
1 Mobilization 1 LS $250 $250
2 AC Pavement 0 SF $10 $0
3 PCC Pad & Sidewalk 125 SF $12 $1,500
4 PCC Access Ramp 0 SF $15 $0
5 Construct Curb and Gutter 0 LF $40 $0
6 Install Truncated Dome 0 SF $45 $0
7 Install Cobblestone 0 SF $40 $0
8 Remove and Restore Landscaping and Irrigation 0 LS $500 $0
9 Remove Cobblestone 125 SF $5 $625
10 Adjust Pull Box to grade 0 EA $150 $0
11 Relocate Sign 1 EA $350 $350
12 Traffic Control 1 LS $125 $125
Subtotal $2,850
10% Contigency $285
Total $3,135
Design and inspection Fees $600
PROJECT TOTAL COST $3,735
TDA FUNDS (80%) $2,988
LOCAL FUNDS (20%) MATCH $747
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2017/2018 - FY 2018/2019
1. Bus Stop No.: 2
2. Project Title: Arrow Route Bus Pad, West of Archibald Ave.
3. Project Description (attach photos and more thorough description as appropriate):
Construct concrete bus pad, AC sidewalk and concrete access ramp. This project
will provide transit riders easier access to local businesses. It will improve access
for disabled riders by providing connection from the bus stop to the existing
sidewalk. The project will be constructed within the existing right of way.
4. Location: North side of Arrow Rte, West of Archibald Ave.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 23,314
6. Non-TDA Article 3 Project Matching Funds: $ 4,663
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 18,651
8. Location Characteristics:
85 Bus Routes Serving Location
34 Number of Daily Buses Serving Location
10 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Arrow Route from Hellman Ave. to Center Ave. (Table 5.89)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by industrial complexes and single family units. Route 85
provides service to or stops within the proximity of: Chino-Upland-Rancho
Cucamonga Civic Center, Chino-Montclair-Chaffey Transit Center, Montclair
Plaza, San Bernardino County Offices, San Antonio Hospital, Kaiser Clinic,
Chino-Montclair-Los Osos High School and Chaffey College.
North side of Arrow Rte., West of Archibald Ave., looking west.
North side of Arrow Rte., West of Archibald Ave., looking east.
Bus Stop 2
Arrow Rte. (N/S & West Bound), West of Archibald Ave.
Item No. Item Quantity Unit Unit Cost Total
1 Mobilization 1 LS $1,000 $1,000
2 AC Pavement 625 SF $10 $6,250
3 PCC Pad & Sidewalk 250 SF $12 $3,000
4 PCC Access Ramp 370 SF $15 $5,550
5 Construct Curb and Gutter 60 LF $40 $2,400
6 Install Truncated Dome 12 SF $45 $540
7 Install Cobblestone 0 SF $40 $0
8 Remove and Restore Landscaping and Irrigation 0 LS $500 $0
9 Remove Cobblestone 0 SF $5 $0
10 Adjust Pull Box to grade 2 EA $150 $300
11 Relocate Sign 1 EA $350 $350
12 Traffic Control 1 LS $500 $500
13 Crosswalk Striping 162 LF $3 $486
Subtotal $20,376
10% Contigency $2,038
Total $22,414
Design and inspection Fees $900
PROJECT TOTAL COST $23,314
TDA FUNDS (80%) $18,651
LOCAL FUNDS (20%) MATCH $4,663
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2017/2018 - FY 2018/2019
1. Bus Stop No.: 3
2. Project Title: Milliken Ave. Bus Pad, South of Church St.
3. Project Description (attach photos and more thorough description as appropriate):
Construct concrete bus pad, concrete sidewalk and concrete access ramp. This
project will provide transit riders easier access to local businesses. It will improve
access for disabled riders by providing connection from the bus stop to the
existing sidewalk. The project will be constructed within the existing right of way.
4. Location: West side of Milliken Ave., South of Church St.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 27,724
6. Non-TDA Article 3 Project Matching Funds: $ 5,545
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 22,179
8. Location Characteristics:
82 and 85 Bus Routes Serving Location
51 Number of Daily Buses Serving Location
10 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Milliken Ave. from Base Line Rd. to Arrow Rte. (Table 5.89)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by industrial complexes and single family units. Route 82
and 85 provides service to or stops within the proximity of: Chino-Upland-
Rancho Cucamonga Civic Center, Chino-Montclair-Chaffey Transit Center,
Montclair Plaza, San Bernardino County Offices, San Antonio Hospital, Kaiser
Clinic, Chino-Montclair-Los Osos High School, Chaffey College, Citizen
Business Bank Arena, Metrolink, Victoria Gardens and Ontario Mills Mall.
West side of Milliken Ave., South of Church St., looking north.
West side of Milliken Ave., South of Church St., looking south.
Bus Stop 3
Milliken Ave. (W/S & South Bound), South of Church St.
Item No. Item Quantity Unit Unit Cost Total
1 Mobilization 1 LS $2,000 $2,000
2 Remove AC Pavement 140 SF $5 $700
3 PCC Pad & Sidewalk 700 SF $12 $8,400
4 PCC Access Ramp 585 SF $15 $8,775
5 Construct Curb and Gutter 52 LF $40 $2,080
6 Install Truncated Dome 24 SF $45 $1,080
7 Install Cobblestone 0 SF $40 $0
8 Remove and Restore Landscaping and Irrigation 0 LS $500 $0
9 Remove Cobblestone 0 SF $5 $0
10 Adjust Pull Box to grade 0 EA $150 $0
11 Relocate Sign 1 EA $350 $350
12 Traffic Control 1 LS $1,000 $1,000
Subtotal $24,385
10% Contigency $2,439
Total $26,824
Design and inspection Fees $900
PROJECT TOTAL COST $27,724
TDA FUNDS (80%) $22,179
LOCAL FUNDS (20%) MATCH $5,545
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2017/2018 - FY 2018/2019
1. Bus Stop No.: 4
2. Project Title: Church St. Bus Pad, West of Day Creek Blvd.
3. Project Description (attach photos and more thorough description as appropriate):
Construct concrete bus pad between the curb and sidewalk. This project will
provide transit riders easier access to local businesses. It will improve access for
disabled riders by providing connection from the bus stop to the existing
sidewalk. The project will be constructed within the existing right of way.
4. Location: North side of Church St., West of Day Creek Blvd.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 5,682
6. Non-TDA Article 3 Project Matching Funds: $ 1,136
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 4,546
8. Location Characteristics:
82 Bus Routes Serving Location
17 Number of Daily Buses Serving Location
8 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Church St. from Rochester Ave. to Victoria Gardens Ln. (Table 5.89)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by single family units. Route 82 provides service to or
stops within the proximity of: Citizens Business Bank Arena, Metrolinks, Victoria
Gardens, Ontario Mills, Kaiser Hospital, Fontana Adult School, and Jurupa, A.B.
Miller and Summit High Schools.
North side of Church St., West of Day Creek Blvd., looking west.
North side of Church St., West of Day Creek Blvd., looking east.
Bus Stop 4
Church St. (N/S & West Bound), West of Day Creek Blvd.
Item No. Item Quantity Unit Unit Cost Total
1 Mobilization 1 LS $400 $400
1 AC Pavement 0 SF $10 $0
2 PCC Pad & Sidewalk 335 SF $12 $4,020
3 PCC Access Ramp 0 SF $15 $0
4 Construct Curb and Gutter 0 LF $40 $0
5 Install Truncated Dome 0 SF $45 $0
6 Install Cobblestone 0 SF $40 $0
7 Remove and Restore Landscaping and Irrigation 0 LS $500 $0
8 Remove Cobblestone 0 SF $5 $0
9 Adjust Pull Box to grade 0 EA $150 $0
10 Relocate Sign 0 EA $350 $0
11 Traffic Control 1 LS $200 $200
Subtotal $4,620
10% Contigency $462
Total $5,082
Design and inspection Fees $600
PROJECT TOTAL COST $5,682
TDA FUNDS (80%) $4,546
LOCAL FUNDS (20%) MATCH $1,136
SUMMARY
Bus Stop Street Side Location Total Cost TDA Funds (80%)Local Funds (20%)
1 Arrow Rte.North East of Malachite Ave.$3,735 $2,988 $747
2 Arrow Rte. North West of Archibald Ave.$23,314 $18,651 $4,663
3 Milliken Ave.West Side South of Church St.$27,724 $22,179 $5,545
4 Church St.North Side West of Day Creek Ave.$5,682 $4,546 $1,136
Total $60,454 $48,363 $12,091
Rounded $60,000 $48,000 $12,000
Date Action
September 9, 2019 Begin Design
October 11, 2019 Complete Design
October 22, 2019 Seek Pemission to Advertise for Bids
November 12, 2019 Open Bids
December 4, 2020 Award project to qualified bidder
January 6, 2020 Begin construction
January 17, 2020 Complete Construction
Bienneial Article 3 20% Fund - FY 2017/2018 & FY 2018/2019
Project Schedule
CITY OF RANCHO CUCAMONGA”N.T.S.RANCHOCUCAMONGA