RE: FY 19/20 TDA Article 3 Thunderbird Road Bus Turnout Award – Scope Change
Dear Mr. Miller:
This letter serves as a response granting the Town of Apple Valley’s November 18, 2020 request to modify the
Transportation Development Act (TDA) Article 3 grant funded project scope as outlined below.
Original Revision
Project Description Thunderbird Road Bus Turnout (unable to
affordably acquire needed ROW)
Bear Valley Road and Navajo Road
Turnout (comparable project in a
different location)
Allocation Number L20-TAV-07 No Change
TDA Article 3 Award $53,897 No Change
Local Match $75,043 No Change
Local Share 58.20% No Change
ATP Share (if applicable) NA No Change
Total Project Cost $128,940 No Change
Deadline 12/31/2022 No Change
Extension Number* 0 No Change
*As long as the project is progressing, SBCTA staff has the authority to grant two one year extension s.
Additional extensions must be approved by the SBCTA Board.
As a friendly reminder, the TDA Article 3 grant award is paid through a reimbursement process upon project
completion. It is required that a TDA claim form and supporting documentation of project completion is
submitted to SBCTA prior to disbursement of funds. The TDA Article 3 grant award is for a maximum
reimbursable amount. Should your project exceed the maximum reimbursable amount, S BCTA will not
provide any additional reimbursement. For projects completed under the awarded amount, SBCTA will
reimburse your agency for the TDA Article 3 share of the project using the match percentage identified above
and in your grant application.
Upon project completion, please contact me for the TDA Claim Form and filing instructions.