Art3_RanchoCucamonga_FY17_Transit_AppCITY OF RANCHO CUCAMONGA
SUMMARY
Bus Stop Street Side Location Total Cost TDA Funds (80%)Local Funds (20%)
1 Lemon Ave.North East of Filkins Ave.$8,608 $6,886 $1,722
2 Milliken Ave.West South of Victoria Park Lane $10,891 $8,713 $2,178
3 Milliken Ave.East North of Central Park $5,880 $4,704 $1,176
4 Aspen St.North West of Red Oak St.$21,721 $17,377 $4,344
5 Etiwanda Ave.East North of Base Line Rd.$7,160 $5,728 $1,432
Total $54,259 $43,407 $10,852
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2016/2017 - FY 2017/2018
1. Bus Stop No.: 1
2. Project Title: Lemon Ave. Bus Pad, East of Filkins Ave.
3. Project Description (attach photos and more thorough description as appropriate):
Install concrete bus pad between the curb and sidewalk. This project will provide
transit riders easier access to local businesses. It will improve access for disabled
riders by providing connection from the bus stop to the existing sidewalk. The
project will be constructed within the existing right of way.
4. Location: North side of Lemon Ave, East of Filkins Ave.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 8,608
6. Non-TDA Article 3 Project Matching Funds: $ 1,722
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 6,886
8. Location Characteristics:
67 Bus Routes Serving Location
15 Number of Daily Buses Serving Location
1 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
N/A
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by single family residentials. Route 67 provides service to
or stops within the proximity of: Alta loma High School, Rancho Cucamonga
High School, Etiwanda High School, Chaffey College and Chaffey Transit
Center.
North side of Lemon Ave., East of Filkins Ave., looking east.
North side of Lemon Ave., East of Filkins Ave., looking west.
Bus Stop 1
Lemon Ave. (N/S & West Bound), East of Filkins Ave.
Item No.Item Quantity Unit Unit Cost Total
1 AC Pad & Sidewalk 0 TON $180 $0
2 PCC Pad & Sidewalk 418 SF $12 $5,016
3 PCC Access Ramp 0 SF $14 $0
4 PCC Retaining Curb 0 LF $32 $0
5 Install Cobblestone 0 SF $26 $0
6 Remove and Restore Landscaping and Irrigation 1 LS $500 $500
7 Adjust Pull Box to grade 0 EA $125 $0
8 Relocate Sign 1 EA $400 $400
9 Relocate Bench 0 EA $300 $0
10 Traffic Control 1 LS $1,000 $1,000
Subtotal $6,916
10%Contigency $692
Total $7,608
Design and inspection Fees $1,000
PROJECT TOTAL COST $8,608
TDA FUNDS (80%)$6,886
LOCAL FUNDS (20%) MATCH $1,722
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2016/2017 - FY 2017/2018
1. Bus Stop No.: 2
2. Project Title: Milliken Ave. Bus Pad, South of Victoria Park Lane
3. Project Description (attach photos and more thorough description as appropriate):
Install concrete bus pad between the curb and sidewalk. This project will provide
transit riders easier access to local businesses. It will improve access for disabled
riders by providing connection from the bus stop to the existing sidewalk. The
project will be constructed within the existing right of way.
4. Location: West side of Milliken Ave., South of Victoria Park Lane
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 10,891
6. Non-TDA Article 3 Project Matching Funds: $ 2,178
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 8,713
8. Location Characteristics:
85 Bus Routes Serving Location
34 Number of Daily Buses Serving Location
4 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Milliken Ave. from SR-210 to Fairmont Way (Table 5.71)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by single family residentials. Route 85 provides service to
or stops within the proximity of: Montclair High School, Montrclair Transit
Center, San Antonio Hospital, San Bernardino County Offices, Kaiser Clinic,
Rancho Cucamonga Metrolink Station, Rancho Cucamonga Central Park, Los
Osos High School, Chaffey College and Chaffey Transit Center.
West side of Milliken Ave., South of Victoria Park Lane., looking north.
West side of Milliken Ave., South of Victoria Park Lane., looking south.
Bus Stop 2
Milliken Ave. (W/S & South Bound), South of Victoria Park Lane
Item No.Item Quantity Unit Unit Cost Total
1 AC Pad & Sidewalk 0 TON $180 $0
2 PCC Pad & Sidewalk 591 SF $12 $7,092
3 PCC Access Ramp 0 SF $14 $0
4 PCC Retaining Curb 0 LF $32 $0
5 Install Cobblestone 0 SF $26 $0
6 Remove and Restore Landscaping and Irrigation 1 LS $500 $500
7 Adjust Pull Box to grade 0 EA $125 $0
8 Relocate Sign 1 EA $400 $400
9 Relocate Bench 0 EA $300 $0
10 Traffic Control 1 LS $1,000 $1,000
Subtotal $8,992
10%Contigency $899
Total $9,891
Design and inspection Fees $1,000
PROJECT TOTAL COST $10,891
TDA FUNDS (80%)$8,713
LOCAL FUNDS (20%) MATCH $2,178
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2016/2017 - FY 2017/2018
1. Bus Stop No.: 3
2. Project Title: Milliken Ave. Bus Pad, North of Central Park
3. Project Description (attach photos and more thorough description as appropriate):
Install concrete bus pad between the curb and sidewalk. This project will provide
transit riders easier access to local businesses. It will improve access for disabled
riders by providing connection from the bus stop to the existing sidewalk. The
project will be constructed within the existing right of way.
4. Location: East side of Milliken Ave., North of Central Park
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 5,880
6. Non-TDA Article 3 Project Matching Funds: $ 1,176
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 4,704
8. Location Characteristics:
85 Bus Routes Serving Location
29 Number of Daily Buses Serving Location
6 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Milliken Ave. from SR-210 to Fairmont Way (Table 5.71)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by single family residentials. Route 85 provides service to
or stops within the proximity of: Montclair High School, Montrclair Transit
Center, San Antonio Hospital, San Bernardino County Offices, Kaiser Clinic,
Rancho Cucamonga Metrolink Station, Rancho Cucamonga Central Park, Los
Osos High School, Chaffey College and Chaffey Transit Center.
East side of Milliken Ave., North of Central Park, looking north.
East side of Milliken Ave., north of Central Park, looking south.
Bus Stop 3
Milliken Ave. (E/S & North Bound), North of Central Park
Item No.Item Quantity Unit Unit Cost Total
1 AC Pad & Sidewalk 0 TON $180 $0
2 PCC Pad & Sidewalk 160 SF $12 $1,920
3 PCC Access Ramp 0 SF $14 $0
4 PCC Retaining Curb 0 LF $32 $0
5 Install Cobblestone 16 SF $26 $416
6 Remove and Restore Landscaping and Irrigation 1 LS $500 $500
7 Adjust Pull Box to grade 0 EA $125 $0
8 Relocate Sign 0 EA $400 $0
9 Relocate Boulders 3 EA $200 $600
10 Traffic Control 1 LS $1,000 $1,000
Subtotal $4,436
10%Contigency $444
Total $4,880
Design and inspection Fees $1,000
PROJECT TOTAL COST $5,880
TDA FUNDS (80%)$4,704
LOCAL FUNDS (20%) MATCH $1,176
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2016/2017 - FY 2017/2018
1. Bus Stop No.: 4
2. Project Title: Aspen St. Bus Pad, West of Red Oak St.
3. Project Description (attach photos and more thorough description as appropriate):
Install concrete bus pad between the curb and sidewalk. This project will provide
transit riders easier access to local businesses. It will improve access for disabled
riders by providing connection from the bus stop to the existing sidewalk. The
project will be constructed within the existing right of way.
4. Location: North side of Aspen St., West of Red Oak St.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 21,721
6. Non-TDA Article 3 Project Matching Funds: $ 4,344
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 17,377
8. Location Characteristics:
85 Bus Routes Serving Location
34 Number of Daily Buses Serving Location
1 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
N/A
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by a church and office professional complexes. Route 85
provides service to or stops within the proximity of: Montclair High School,
Montrclair Transit Center, San Antonio Hospital, San Bernardino County Offices,
Kaiser Clinic, Rancho Cucamonga Metrolink Station, Rancho Cucamonga Central
Park, Los Osos High School, Chaffey College and Chaffey Transit Center.
North side of Aspen St., West of Red Oak St., looking west.
North side of Aspen St., West of Red Oak St., looking east.
Bus Stop 4
Aspen St. (N/S & West Bound), West of Red Oak St.
Item No.Item Quantity Unit Unit Cost Total
1 AC Pad & Sidewalk 0 TON $180 $0
2 PCC Pad & Sidewalk 576 SF $12 $6,912
3 PCC Access Ramp 340 SF $14 $4,760
4 PCC Retaining Curb 145 LF $32 $4,640
5 Install Cobblestone 0 SF $26 $0
6 Remove and Restore Landscaping and Irrigation 1 LS $1,000 $1,000
7 Adjust Pull Box to grade 1 EA $125 $125
8 Relocate Sign 1 EA $400 $400
9 Relocate Bench 0 EA $300 $0
10 Traffic Control 1 LS $1,000 $1,000
Subtotal $18,837
10%Contigency $1,884
Total $20,721
Design and inspection Fees $1,000
PROJECT TOTAL COST $21,721
TDA FUNDS (80%)$17,377
LOCAL FUNDS (20%) MATCH $4,344
Biennial Article 3 20% Fund
Call for Projects Application Form
FY 2016/2017 - FY 2017/2018
1. Bus Stop No.: 5
2. Project Title: Etiwanda Ave. Bus Pad, North of Base Line Rd.
3. Project Description (attach photos and more thorough description as appropriate):
Install concrete bus pad between the curb and sidewalk. This project will provide
transit riders easier access to local businesses. It will improve access for disabled
riders by providing connection from the bus stop to the existing sidewalk. The
project will be constructed within the existing right of way.
4. Location: East side of Etiwanda Ave, North of Base Line Rd.
X Existing Bus Stop _________ New Bus Stop
X Existing ROW _________ Easement Required
5. Project Cost Estimate: $ 7,160
6. Non-TDA Article 3 Project Matching Funds: $ 1,432
Source of Matching Funds: Local Funds
7. Requested Article 3 TDA Call for Project Funds: $ 5,728
8. Location Characteristics:
67 Bus Routes Serving Location
15 Number of Daily Buses Serving Location
6 Daily Boardings and Alightings
9. Relationship to 2011 Non-Motorized Transportation Plan projects, if any:
Etiwanda Ave. from Wilson Ave. to Base Line Rd. (Table 5.71)
10. Listing of Activity Generators and Attractors Served:
The stop is surrounded by single family residentials. Route 67 provides service to
or stops within the proximity of: Alta loma High School, Rancho Cucamonga
High School, Etiwanda High School, Chaffey College and Chaffey Transit
Center.
East side of Etiwanda Ave., North of Base line Rd., looking north.
East side of Etiwanda Ave., North of Base line Rd., looking south.
Bus Stop 5
Etiwanda Ave. (E/S & North Bound), North of Base Line Rd.
Item No.Item Quantity Unit Unit Cost Total
1 AC Pad & Sidewalk 10 TON $180 $1,800
2 PCC Pad & Sidewalk 0 SF $12 $0
3 PCC Access Ramp 0 SF $14 $0
4 PCC Retaining Curb 0 LF $32 $0
5 Install Cobblestone 0 SF $26 $0
6 Remove and Restore Landscaping and Irrigation 0 LS $500 $0
7 Adjust Pull Box to grade 0 EA $125 $0
8 Relocate Sign 1 EA $400 $400
9 Install 2"X4" Header 120 LF $20 $2,400
10 Traffic Control & Striping 1 LS $1,000 $1,000
Subtotal $5,600
10%Contigency $560
Total $6,160
Design and inspection Fees $1,000
PROJECT TOTAL COST $7,160
TDA FUNDS (80%)$5,728
LOCAL FUNDS (20%) MATCH $1,432
Date Action
May 1, 2018 Begin Design
June 28, 2018 Complete Design
July 11, 2018 Seek Pemission to Advertise for Bids
August 7, 2018 Open Bids
September 5, 2018 Award project to qualified bidder
September 24, 2018 Begin construction
October 18, 2018 Complete Construction
Bienneial Article 3 20% Fund - FY 2016/2017 & FY 2017/2018
Project Schedule