Art3_Highland_FY17_Transit_AppEXHIBIT "A"
ID
No.
Transit
Stop # Transit Stop Location
Number of
Daily
Buses
serving
location
Daily
Boarding
s
Daily
Alightings
Bus
Route No.
1 6008 North Side Base Line west of Cole Avenue 59 7 7 3/4
2 6009 North Side Base Line east of Central Avenue 59 16 16 3/4
3 6010 North Side Base Line west of Vine Street 59 8 7 3/4
4 6011 North Side Base Line west of Victoria Avenue 59 13 10 3/4
5 6014 North Side Base Line at Guthrie Street 59 5 6 3/4
6 6015 North Side Base Line west of Sterling Avenue 59 41 23 3/4
7 8141 North Side Base Line west of Osbun Road 59 22 13 3/4
8 304 Street 32 14 3 15
9 305 Street 32 5 11 15
10 449 Boulder Ave northbound north of Baseline St 60 65 38 3
11 6006 southbound 56 9 21 4
12 6269 midblock 60 2 2 3
13 6268 Boulder Ave at Pacific southbound midblock 56 3 2 4
14 5709 Boulder Ave at Pacific northbound farside 60 2 2 3
15 6003 Boulder Ave at Pacific southbound farside 56 1 2 4
16 5710 Boulder Ave at Atlantic northbound farside 60 2 3 3
17 6002 Boulder Ave at Atlantic southbound farside 56 0 0 4
18 6001 Boulder Ave at Highland southbound farside 56 64 77 4
Totals: 279 243
Combined Total:522
OMNITRANS TRANSIT STOP SURVEY
EXHIBIT “B”
EXHIBIT “C1”
PROPOSED CROSSWALK WITH IN-ROADWAY WARNING LIGHTS ON
CENTRAL AVENUE AT HIBISCUS STREET
BUS ROUTE No. 15
Central Avenue Speed Limit: 25mph
2030 Projected Traffic Volume on Central Avenue: 6,800vpd
Pedestrian Generators within 300’ of proposed crosswalk on Central Avenue
Cypress Elementary School
Athletic Center
YMCA
Library
Environmental Learning Center
Community Park
Cypress
Elementary School
Library/YMCA/
Environmental Learning
Center/ Central Park
Transit
Stop
#0305
Transit
Stop
#0304
Cypress Street Central Avenue 375’
Bus
Route
#15
Bus
Route
#15
Proposed New High-Visibility
Crosswalk with In-Roadway
Warning Lights
N
EXHIBIT “C2”
PROPOSED CROSSWALK WITH IN-ROADWAY WARNING LIGHTS
ON CENTRAL AVENUE AT HIBISCUS STREET
BUS ROUTE No. 15
Transit Stop
No. 0305
Transit Stop
No. 0304
Construct
Ramp
Existing Ramp
Proposed
New Lighted
Crosswalk
CYPRESS
E.S.
LIBRARY,
YMCA/ENVIRONMENTAL
LEARNING CENTER CENTRAL AVE HIBISCUS ST
N
EXHIBIT “C3”
This project will construct concrete transit stop
landing area on the west side of Central Avenue
south of Hibiscus Street at Transit Stop No. 0305
on Bus Route No. 15.
Existing
Sidewalk
Existing
Curb
Construct
Concrete
Typical Obstruction Clearance
This project will widen sidewalk around
obstructions to provide minimum 4’ clearance for
improved transit stop access along Bus Route Nos.
3, 4 and 15. Existing fence will be relocated as
needed.
EXHIBIT “C4”
PROPOSED WIDENINGS AROUND SIDEWALK OBSTRUCTIONS
Indicates Location of Sidewalk Widening to provide ADA clearance Around Obstruction
Indicates Relocate Fence
Transit
Stop
#6011 Sterling Ave
Transit
Stop
#6010
Transit
Stop
#6009
Transit
Stop
#6008
Transit
Stop
#8141
Transit
Stop
#6015
Transit
Stop
No#
Relocate
Fence Rogers Ln Elm St Guthrie St Central Ave Cole Ave Vine St Victoria Ave BASE LINE – Bus Route No’s 3 and 4
BASE LINE – Bus Route No’s 3 and 4
N
EXHIBIT “D”
PROPOSED ACCESS IMPROVEMENTS ON BOULDER AVENUE
BUS ROUTE No. 4
Indicates Location of Curb Ramp Modification
Indicates Location of Bus Stop
Indicates Bus Route
Atlantic Ave
Pacific St Guthrie St Boulder Avenue – Bus Route No 4
Beaver Medical
Center
Albertsons Shopping
Center Base Line – Bus Route No. 15 Highland Avenue- Bus Route No. 4
EXHIBIT "E"
Agency:
Project Name:
Project Location:
Date of Estimate:
Prepared by:
Item No.Description Quantity Units Unit Cost Total
1 Install High-Visibility Crosswalk Markings on Central Ave Route #15 at Hibiscus St 1 EA 1,000$ $1,000
2 Install In-Roadway Warning Lights on Central Ave Route #15 at Hibiscus St 1 LS 45,000 $45,000
3 Construct New Curb Ramp at Central Ave/Hibiscus St 1 EA 3,500 $3,500
4 Construct New Concrete Landing at Transit Stop #0305 on west side Central Avenue near Hibiscus St 400 SF 10 $4,000
5 Construct Sidewalk Widening Around Obstructions (Route No's 3, 4 and 15)7 EA 1,000 $7,000
6 Relocate Fence on Sterling to make way for sidewalk widenings between Route No's 3, 4 and 15 600 LF 35 $21,000
7 Ramp Modifications for improved ADA access on Boulder Ave (Route #4)10 EA 3,000 $30,000
8 Install truncated domes for improved ADA access on existing Ramps on Boulder Avenue (Route #4)18 EA 600 $10,800
Subtotal:$122,300
Contingencies:$18,345
Mobilization:$6,000
SWPPP:$3,500
Traffic Control:$6,000
Construction Subtotal:$156,145
Construction Engineering:$23,422
Construction:$179,567
PS&E:$39,036
Total:$218,603
David Kinzle
Detailed Engineer's Estimate
For Construction Items Only
City of Highland
Transit Access Improvements along Bus Route Nos. 3, 4 and 15
Base Line, Boulder Avenue and Central Avenue in the City of Highland
June 28, 2017
EXHIBIT “F”
SURVEY AREA for
obstructions in
pedestrian paths