Art3_Redlands_2026 Active Project StatusFrom:Veronica Medina
To:Lisa Chou
Cc:Ginger Koblasz
Subject:RE: TDA Article 3 Annual Report - Redlands
Date:Monday, June 22, 2026 7:56:48 AM
Attachments:image001.png
CAUTION: This email originated from outside of the organization. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Hi Lisa,
Please see responses in the table below. Please let me know if you have any questions.
Thanks,
Veronica Medina, E.I.T.
Associate Engineer
Municipal Utilities & Engineering Department
City of Redlands
Office: (909) 798-7584 ext. 6
From: Lisa Chou <lchou@gosbcta.com>
Sent: Friday, June 19, 2026 2:33 PM
To: Veronica Medina <vmedina@cityofredlands.org>
Cc: Ginger Koblasz <gkoblasz@gosbcta.com>
Subject: TDA Article 3 Annual Report - Redlands
CAUTION: This message originated outside of the City of Redlands. Do NOT click links or open attachments unless you are certain the content is safe.
If suspected as Malicious or Phishing, report using the Phish Alert Button (PAB). If suspected as Spam, use the "Report as Junk" button.
Good afternoon,
Could you help provide an update on the highlighted sections of Redlands’ Active Transportation Development Act (TDA) Article 3 award?
Award
Fiscal
Year
Agency Description Project
Type TDA3 Local
Share
Current
Deadline Status
Estimate of
Expenses
to Date
Contractor
Selected
(yes or no)
Able to
Complete
by
Deadline
(yes or no)
23/24 Redlands Orange Blossom
Trail Phase IV
Bike/Ped $1,089,700 $192,300 6/30/2027 Completed NOC
6/2/26
Awaiting closeout
documents to
release retention.
$936,852.08
Yes
Tryco General
Engineering
Yes
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any
potential issues and limit the number of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting
requirement, awardees must also demonstrate expenditure of some funds within ONE year of award notification and, for construction contracts, a contract
must be awarded within THREE years of award notification. We expect there to be some leniency for existing awards, particularly with the one year expenditure
rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete the project by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) or feel free to reach out to me directly with questions.
Thank you,
Lisa Chou, AICP
San Bernardino County Transportation Authority
Contract Planner
1170 West Third Street, 2nd Floor
San Bernardino, CA 92410
Office: 626.204.9801 Cell: 626.630.6127
The information in this e-mail and any attachments are for the sole use of the intended recipient and may contain privileged and confidential information. If you
are not the intended recipient, any use, disclosure, copying or distribution of this message or attachment is strictly prohibited. If you believe that you have
received this e-mail in error, please contact the sender immediately and delete the e-mail and all of its attachments.
This message contains confidential information and is intended only for the individual(s) addressed in the message. If you are not the named addressee, you should not
disseminate, distribute, or copy this e-mail. If you are not the intended recipient, you are notified that disclosing, distributing, or copying this e-mail is strictly prohibited.