Loading...
Art3_AppleValley_FY25_SidewalkRemediation_AwardNovember 06, 2025 Julie Ryan Transmitted via email to: jryan@applevalley.org RE: Apple Valley Road Sidewalk Remediation Project Dear Julie Ryan, It is our pleasure to inform you that on November 5, 2025, the San Bernardino County Transportation Authority (SBCTA) Board of Directors (Board) approved funding in the amount of $95,000 from the Transportation Development Act (TDA) Article 3 Bicycle and Pedestrian Facilities Program for the Apple Valley Road Sidewalk Remediation Project. The SBCTA Board set the period of time for completion of your project to comply with TDA provisions, therefore this project must be completed by June 30, 2029. Please note the following important funding requirements: •A (1) signed Claim Form and (2) and Authorizing Resolution Authorized Resolution must be submitted within six months (by May 07, 2026) of project award notification, or prior to requesting reimbursement of funds, whichever comes first. A sample resolution can be found at www.gosbcta.com/tda3 under the Claims section. •Completion of an Annual Proof of Progress Report (Annual Report) must be submitted on the FIRST anniversary of award notification AND by June 30 for all subsequent years thereafter. The annual report must include: o A description of the work completed during the year, o An estimate of the total project percent completed, and o An estimate of the amount spent to-date. •Funds will be rescinded if no progress has been made within ONE year of award notification or if, where appropriate, a construction contract has not yet been awarded within THREE years of award notification. Additionally, the TDA Article 3 award is paid through a reimbursement process. The award is for a maximum reimbursable amount. Should your project exceed the maximum reimbursable amount, SBCTA will not provide any additional reimbursement. Congratulations on submitting a successful grant application. We look forward to the timely completion of your project. Should you have any questions please contact me at (909) 884-8276 or gkoblasz@gosbcta.com. Sincerely, Ginger Koblasz Data & Analytics Program Manager