Loading...
Attachment-f-project-estimate_Highland-Redlands Connector Gap ProjectATP - Application Instructions for Detailed Project Estimate and Total Project Cost- Cycle 7 • Applicants are expected to use this template for estimating/documenting the cost of construction items and the overall project costs. (Eligible and Ineligible) •The Detailed Engineer's Estimate and Total Project Costs must tie to the information presented in Part A through C of the ATP Application Form. • Do NOT input values in gray cells. These cells are formula-driven and will automatically update. Project (Engineer's) Information • The Licensed Engineer in 'responsible charge' of the overall ATP application must review all information presented in this Estimate form and ensure the values are consistent with the corresponding plans included in the application. This requirement is considered necessary to ensure the ATP application meets the CTC's PSR-Equivalent requirement - including the use of construction items, quantities and unit prices that meets industry standards for PSR-Equivalents. The engineer is also expected to review the breakdown of eligible (participating) vs. ineligible (non-participating) costs shown in estimate and confirm they are consistent with the ATP Guidelines and ATP Eligible Infrastructure Costs Guidance. Engineer's Estimate & Cost Breakdown For each construction item in this table, the following items must be filled: Item: indicate the name of a construction item used in this project. Quantity: indicate the total quantity of each construction item Units: indicate the units of measurement (i.e. Square Feet or SQFT.) Only use Lump Sum (LS) for items listed on the Allowable Lump Sum tab. Unit Cost: indicate the unit cost for one quantity. Note: Unit Cost estimate should be escalated forward to the date of anticipated mid-point of construction using available forecasted indices for construction cost escalation and/or inflation. Total Item Cost will be automatically calculated once the above information are provided for each line item (row). The Project Estimate form only has a limited number of lines. If your estimate has more items; you will have to combine similar items. If an applicant has already developed a complete estimate using another tool, the items can be grouped into sub-categories such as overhead, bike lanes, sidewalks, drainage, utilities etc., as long as the full estimate is attached to the estimate or with the application in the Additional Attachments section. General Overhead: Costs for these items have been separated out to reduce confusion relating to eligible vs. ineligible costs calculations. The % of eligible vs. ineligible costs are automatically calculated based on the ratio of these costs for all of the other construction items. Cost Breakdown See ATP Eligible Infrastructure Costs Guidance for details on eligible and ineligible items located here: https://dot.ca.gov/-/media/dot-media/programs/local-assistance/do cuments/atp/general-and-technical-info/final-eligible-infrastructure-costs-guidance20231220.pdf ATP Eligible Items/costs: these are expected to represent all construction items that are ATP eligible. %- Insert the percentage of the total item cost that is directly attributed to "ATP Eligible items". $- This field will automatically calculate once a percentage is entered in the previous question. ATP Ineligible (non-participating) Items/costs: these are expected to represent all construction costs that are not ATP eligible. The % and costs are automatically calculated based on the "%" value the applicant entered for the eligible costs. To be constructed by Corps/CCC: these are expected to include all items & costs that will be constructed by the Corps/CCC. %- Insert the percentage of the total item cost that is directly attributed to "Corps/CCC to construct". $- This field will automatically calculate once a percentage is entered in the previous question. Subtotals and Contingencies: Subtotal of Construction Items: This field will automatically calculate the total of all construction items indicated above. Construction Item Contingencies: Contingency compensates for the use of limited information available during early phases of a project. Insert percentage of contingencies, which is intended to account for the cost of minor construction items not defined at the time the ATP applications are prepared. The amount for contingency varies for project capital cost estimates rather it is risk-based contingency for identified known risks and additional or residual contingency for unidentified undetermined risks, such as unrefined scope adjustments, unit cost uncertainties, and construction phase uncertainties. Total (Construction Items and Contingencies) Cost: This field will automatically calculate the total from all information indicated above. Project Delivery Costs: The eligible vs. ineligible split is automatically calculated for all Project Delivery Costs. Project Approval & Environmental Document (PA&ED): Total cost of Environmental Studies and Permits phase of the project. Note: Cost estimate should be escalated forward to the date of anticipated mid-point of the activities using available forecasted indices for PA&ED escalation and/or inflation. Plans, Specifications & Estimate (PS&E): Total cost of Plans, Specifications and Estimates phase of the project. Note: Cost estimate should be escalated forward to the date of anticipated mid-point of the activities using available forecasted indices for PS&E escalation and/or inflation. Total Preliminary Engineering (PE): This total is automatically calculated. Total of (PA&ED) + (PS&E) Note: Per the Caltrans Local Assistance Procedures Manual, the total cost for PE should not exceed 25%. All costs over the 25% must be shown in the application as ineligible (non-participating). Right of Way Engineering: Total cost of Right of Way Engineering, including obtaining the RW Certification. Note: Cost estimate should be escalated forward to the date of anticipated mid-point of the activities using available forecasted indices for right of way engineering cost escalation and/or inflation. Acquisitions and Utilities: Total cost of Acquisitions and Utilities. Note: Cost estimate should be escalated forward to the date of anticipated mid-point of the activites using available forecasted indices for aquisition and utility cost escalation and/or inflation. Total RW: This total is automatically calculated. Total of (RW Eng.) + (Acq.&Utilities) Total Pre-Construction Costs: This total is automatically calculated. Total of (PE) + (RW) Construction Engineering (CE): Total cost of Construction Engineering. Note: Cost estimate should be escalated forward to the date of anticipated mid-point of construction using available forecasted indices for construction cost escalation and/or inflation. Per the Caltrans Local Assistance Procedures Manual, the total cost for CE should not exceed 15%. All costs over the 15% must be shown in the application as ineligible (non-participating). Total Construction Costs: This total is automatically calculated. Total of (CE) + (Con. Item. & Contig.) Total Project Cost Estimate: The eligible vs. ineligible split is automatically calculated for the Total Project Costs. • This is automatically calculated from all information entered above. • This value must represent the total estimated cost of the entire ATP project. • The application must account for the ineligible (non-participating) costs being funded with local funds. Note: Local funding for ineligible (non-participating) costs cannot be considered as leveraging and/or match funds. Documentation of Eligible (Participating) and/or Ineligible (Non-Participating) Costs: The following is an example of how Engineer's can present their logic and calculations for splitting the projects costs between eligible (participating) and ineligible (non-participating) costs. Example #1 - Pavement Rehabilitation: The paving and base repair needed for the 1,000 linear feet two-lane roadway is within the limits of the new 5-foot Class II bike lanes with 3-foot buffer and 11-foot vehicular lanes in each direction. The area within the physical limits of the new bike lanes and buffer is estimated to be 2 x ((5+3) ft x 1,000 ft) = 16,000 sqft and the area outside these limits is estimated to be 2 x 11 ft x 1,000 ft = 22,000 sqft. The ATP eligible reimbursement for all costs related to the Pavement Rehabilitation is calculated to be 16,000/(16,000+22,000) = 42%. This split was used for Hot Mix Asphalt, Aggregate Base, and Excavation. Do not attach these instructions to the ATP application Item No. General Overhead-Related Construction Items 1 2 3 4 5 6 7 8 9 10 General Construction Items 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 Documentation of Eligible (Participating) and/or Ineligible (Non-Participating) Costs: The Engineer's justification for including typical ATP-Ineligible items in the ATP-Eligible column and logic and/or calculations for splitting costs between ATP-Eligible and Ineligible costs must be documented in this section of the Estimate form. Separate justification is required for each item which is partly ineligible for ATP funding or is required for the construction of an ineligible item/element of the project. Item #: Important: Read the Instructions in the first sheet (tab) before entering data. Do not enter data in shaded fields (with formulas). Agency: Mobilization Traffic Control Stormwater Protection Plan Construction Survey & Monumentation Restortation Clearing and Grubbing Unclassified Excavation Site Grading (Cut) Site Grading (Fill) Site Import Remove Ex. Scrubs, Trees, & Roots. D<36" Remove Ex. Scrubs, Trees, & Roots. D>36" Construct 8" AC Dike per City of Highland or Redlands Std Plan Construct 8" PCC C&G per City of Highland Std Plan Construct 4" AC Trail Construct 6" Crushed Miscellanous Base Construct 4" PCC Trail over 90% Compacted Native Construct 4" PCC Sidewalk Construct PCC Curb Ramp per SPPWC Std Plan Construct AC Driveway Approach per SPPWD Std Plan 1.5" Min. Cold Plan Overlay 1.5" Thickness Construct Retaining Wall per SPPWC Std Plan 618-3, Case 1 Type B Water Valve/Water Meter Boxes to be Adjusted to Grade Construct CMP, Drain Pipe, Size Shown Construct Gate per City of Highland Std Plan 509B Construct Removable Bollards per Plan Construct Type 842 Barrier per Caltrans Std Plan B11-60 Construct Curb Opening Catch Basin per SPPWC Std Plan No. 300-3 Construct Curb Outlet Strucutre per City of Highland Std Plan 210A Relocate Existing Fire Hydrant Construct 4" AC Pavement Construct 6" Crushed Miscellanous Base Install 20 Feet K-Rails Restore Irrigation and Landscape In-Kind Construct Pre-Fabricated Bridge and Abutment. Location "1" Construct Pre-Fabricated Bridge and Abutments. Location "2" Construct Pre-Fabricated Bridge and Abutments. Location "3" Install Guard Rail per Caltrans Std Plan A77L1, A77N6 & A77R4 (Type 16B) including End Treatment MSKT-MGS or equal Install Pedestrian Light (Solar/LED) Install Metal Hand Railings per SPPWD Std Plan No. 606-4, Type A Relocate Existing Street Light Adjust manhole Frame and Cover to Grade Signing and Striping Traffic Signal Location 1 (Cemex and Orange St) and Location 2 (Greenspot/5th and Orange St) Environmental Mitigation Cost (Endanger Species) Detailed Project Estimate and Total Project Costs - Cycle 7 San Bernardino County Transportation Authority Project Description: Project Location: Project Estimate (for Construction Items Only) Item Description of Engineer's Justification: (See example shown in the Instructions) Construction Class I, II, and IV bicycle and pedestrian paths Orange Street from Domestic Ave to Greenspot Road Quantity 1 1 1 1 1 242 4381 8373 4904 41 2 402 133 1473 1058 40492 993 7 32 13697 133 7040 5 53 13 12 504 1 3 1 282 205 2 2 1 1 1 315 11 231 1 28 1 1 1 Units LS LS LS LS LS LS LS LS LS LS LS LS CY CY CY CY EA EA LF LF TON CY SF SF EA TON SF TON SF EA LF LF EA LF LS EA EA TON CY EA LS LS LS LS LF EA LF EA EA LS LS LS Construction Item Contingencies (% of Construction Items): Type of Project Cost Project Approval and Environmental Document (PA&ED): Plans, Specifications and Estimates (PS&E): Total PE: Right of Way Engineering: Acquisitions and Utilities: Total RW: Total Pre-Construction Costs (PE+RW): Construction Engineering (CE): Total Construction Costs: Total Project Cost: Unit Cost 175000 100000 25000 100000 75000 82.65 85.25 82.25 85.25 610 2500 20 60 125 92 10 10 5575 125 0.7 130 81.5 400 320 75 650 550 50000 6250 7000 125 92.5 1500 13000 750000 490000 305000 185 6100 65 13000 785 625000 80000 7780000 Subtotal of Construction Items: 0.1 Total (Construction Items & Contingencies) cost: Project Delivery Costs: Cost $ 150000 600000 900000 17083548.02 Project Information: Project Estimate and Cost Breakdown: Total Item Cost 175000 100000 25000 0 0 0 0 0 0 0 100000 75000 20001.3 373480.25 688679.25 418066 25010 5000 8040 7980 184125 97336 404920 9930 39025 4000 9587.9 17290 573760 2000 16960 975 7800 277200 50000 18750 7000 35250 18962.5 3000 26000 750000 490000 305000 58275 67100 15015 13000 21980 625000 80000 7780000 14030498.2 1403049.82 15433548.02 Preliminary Engineering (PE) 750000 Right of Way (RW) 0 750000 Construction Engineering (CE) 16333548.02 Licensed Engineer in responsible charge of preparing or reviewing this PSR-Equivalent Cost Estimate: ATP Eligible Costs/Items % 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 Reyes S. "Sal' Chavez $ 175000 100000 25000 0 0 0 0 0 0 0 100000 75000 20001.3 373480.25 688679.25 418066 25010 5000 8040 7980 184125 97336 404920 9930 39025 4000 9587.9 17290 573760 2000 16960 975 7800 277200 50000 18750 7000 35250 18962.5 3000 26000 750000 490000 305000 58275 67100 15015 13000 21980 625000 80000 7780000 14030498.2 1403049.82 15433548.02 ATP Eligible Costs 150000 600000 750000 0 0 0 750000 900000 16333548.02 ATP Eligible Costs 17083548.02 Cost Breakdown ATP Ineligible Costs/Items % 0 0 0 1 1 1 1 1 1 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Date: $ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ATP Ineligible Costs 0 0 0 0 0 0 0 0 0 ATP Ineligible Costs 0 4/12/2024 License #: Corps/CCC to construct % "PE" costs / "CON" costs 4.85954363201573E-02 "CE" costs / "CON" costs 5.83145235841888E-02 C41904 $ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 25% Max 15% Max Item Description- Common to ATP CLEARING AND GRUBBING CONSTRUCTION AREA SIGNS CONSTRUCTION SURVEY/STAKING DEVELOP WATER SUPPLY DUST CONTROL EROSION CONTROL FINISHING ROADWAY JOB SITE MANAGEMENT MITIGATION MOBILIZATION MOBILIZATION, DEMOBILIZATION, AND FINAL CLEANUP PERMITS PREPARE STORM WATER POLLUTION PREVENTION PLAN PREPARE WATER POLLUTION CONTROL PROGRAM RAILROAD FLAGGING & MISCELLANEOUS RE OFFICE SIGNS STRIPING TRAFFIC CONTROL SYSTEM TRAFFIC MANAGEMENT PLAN Item Description- Not common to ATP ABANDON SEWER ADL BURIAL LOCATION REPORT ASBESTOS COMPLIANCE PLAN AUTOMATED WORK ZONE INFORMATION SYSTEM BOOSTER PUMP BRIDGE REMOVAL BUILDING WORK CAMERA SYSTEMS CERTIFY EXISTING BACKFLOW PREVENTERS CHANGEABLE MESSAGE SIGN SYSTEM CHECK AND TEST EXISTING IRRIGATION FACILITIES CLEAN AND PAINT BRIDGE RAILING CLEAN AND PAINT STEEL SOLDIER PILING CLEAN AND PAINT STRUCTURAL STEEL CLEAN AND PAINT STRUCTURAL STEEL (EXISTING BRIDGE) CLEAN STRUCTURAL STEEL (EXISTING BRIDGE) CONTRACTOR-SUPPLIED BIOLOGIST (LS) CONTROL AND NEUTRAL CONDUCTORS CONTROL AND NEUTRAL CONDUCTORS (ARMOR-CLAD) DATA CORE DRAINAGE PUMPING EQUIPMENT DUST CONTROL PLAN (NATURALLY OCCURRING ASBESTOS) DUST PALLIATIVE ELECTRIC SERVICE FOR BOOSTER PUMP ELECTRIC SERVICE FOR IRRIGATION FIBER OPTIC CABLE SYSTEMS FISH PROTECTION FLASHING BEACON SYSTEM HEALTH AND SAFETY PLAN INDUCTIVE LOOP DETECTOR (LS) INTELLIGENT COMPACTION INTERCONNECTION CONDUIT AND CABLE (LS) INVASIVE SPECIES CONTROL IRRIGATION WATER SERVICE CHARGES JACKING SUPERSTRUCTURE LEAD COMPLIANCE PLAN LIGHTING SYSTEM-(Electroliers are a seperate item (EA)) MAINTAIN EXISTING PLANTED AREAS MAINTAINING EXISTING TRAFFIC MANAGEMENT SYSTEM ELEMENTS DURING CONSTRUCTION MIX DESIGN (FULL DEPTH RECLAMATION-FOAMED ASPHALT) MIX DESIGN (FULL-DEPTH RECLAMATION-CEMENT) MOBILIZATION (MARINE ACCESS) MODIFY BRIDGE RAILING (LS) MODIFY PUMP PLANT MODIFYING EXISTING ELECTRICAL SYSTEM MONITOR WELL NATURAL RESOURCE PROTECTION PLAN NOA BURIAL LOCATION REPORT NOISE MONITORING OPERATE EXISTING IRRIGATION FACILITIES PAINT STRUCTURAL STEEL (EXISTING BRIDGE) PERMANENT EROSION CONTROL ESTABLISHMENT WORK PLANT ESTABLISHMENT WORK PORTABLE CHANGEABLE MESSAGE SIGN (LS) PREPAVING INERTIAL PROFILER PRESTRESSING PRESTRESSING CAST-IN-PLACE CONCRETE PRESTRESSING PRECAST GIRDER PRESTRESSING STEEL GIRDERS PROGRESS SCHEDULE (CRITICAL PATH METHOD) PRUNE EXISTING PLANTS PUBLIC SAFETY PLAN PUMPING PLANT ELECTRICAL EQUIPMENT PUMPING PLANT EQUIPMENT RADAR SPEED FEEDBACK SIGN SYSTEMS RAMP METERING SYSTEM RECONSTRUCT DRAINAGE FACILITY (LS) RECONSTRUCT FENDER RECYCLED WATER IDENTIFICATION AND WARNING SIGNS REMOVE CONCRETE (LS) REMOVE CONCRETE (MISCELLANEOUS) (LS) REMOVE CONCRETE CURB (LS) REMOVE DOWNDRAIN (LS) REMOVE DRAINAGE FACILITY (LS) REMOVE IRRIGATION FACILITY REMOVE RAILING REMOVE REINFORCED CONCRETE BOX CULVERT (LS) REMOVE RETAINING WALL (LS) REMOVE RETAINING WALL (PORTION) (LS) REMOVE SIGN STRUCTURE (LS) REMOVE SIGN STRUCTURE WALKWAY (LS) REMOVE SLOPE PAVING (LS) REMOVE SOUND WALL (LS) REMOVING EXISTING ELECTRICAL SYSTEM ROADSIDE CLEARING SALVAGE IRRIGATION FACILITY SAMPLING AND ANALYSIS PLAN (NATURALLY OCCURRING ASBESTOS) SIGN ILLUMINATION SYSTEM STAIN GALVANIZED SURFACES (LS) STRAY CURRENT PROTECTION (BRIDGE) STREET SWEEPING TEMPORARY ACTIVE TREATMENT SYSTEM TEMPORARY CONCRETE WASHOUT TEMPORARY CONSTRUCTION MAT (LS) TEMPORARY CREEK DIVERSION SYSTEMS TEMPORARY DECKING TEMPORARY FLASHING BEACON TEMPORARY LIGHTING SYSTEM TEMPORARY PEDESTRIAN ACCESS ROUTE TEMPORARY SHORING TEMPORARY SIGNAL AND LIGHTING TEMPORARY SIGNAL SYSTEM TEMPORARY SUPPORT TIME-RELATED OVERHEAD (LS) TRAFFIC MONITORING STATION SYSTEM WATER METER CHARGES WATER SUPPLY SYSTEM WELL DEVELOPMENT WORK AREA MONITORING (BRIDGE) Unit Pay LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS Unit Pay LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS LS