Art3_Omnitrans_FY19_Transit_BusShelters_Scope_201117
November 17, 2020
Anna Jaiswal
Development Planning Manager
Omnitrans
Sent electronically to Anna.Jaiswal@omnitrans.org
RE: FY19 TDA Article 3 Transit Bus Shelter Award – Scope Change
Dear Ms. Jaiswal:
This letter serves as a response granting Omnitrans’ November 12, 2020 request to modify the Transportation
Development Act (TDA) Article 3 grant funded project scope as outlined below.
Original Revision
Project Description Misc. bus shelters and benches
including:
• Shelter at Citrus @ Judson/Ford EB
(ID 6965)
• Shelter at Riverside @ Vineyard WB
(ID 8409)
Removal of two shelters specified to the
left in exchange for:
• Shelter at Barton @ Terracina EB
(ID 6951)
• Shelter at Holt @ Imperial EB
(ID 5818)
Allocation Number L20-OMN-11 No Change
TDA Article 3 Award $193,126 No Change
Local Match $0 No Change
Local Share 0% No Change
ATP Share (if applicable) NA NA
Total Project Cost $193,126 No Change
Deadline 12/31/2022 No Change
Extension Number* 0 No Change
*As long as the project is progressing, SBCTA staff has the authority to grant two one year extensions.
Additional extensions must be approved by the SBCTA Board.
As a friendly reminder, the TDA Article 3 grant award is paid through a reimbursement process upon project
completion or through progress payments for awards over $200,000. It is required that a TDA claim form and
supporting documentation of project completion or progress are submitted to SBCTA prior to disbursement of
funds. The TDA Article 3 grant award is for a maximum reimbursable amount. Should your project exceed the
maximum reimbursable amount, SBCTA will not provide any additional reimbursement. For projects
completed under the awarded amount, SBCTA will reimburse your agency for the TDA Article 3 share of the
project using the match percentage identified above and in your grant application.
Upon project completion, please contact me for the TDA Claim Form and filing instructions.
Sincerely,
Ginger Koblasz
Cc: Nancy Strickert, SBCTA