Art3_Redlands_FY17_BikePed_EValleyInterconnect_Comm_201028Hi Ginger,
Orange Blossom Trail: The extension request for this grant will be taken to SBCTA board for approval in December/January.
PIIP – Scope Change to HSIP grant: This grant assisted in funding the HSIP Cycle 7 Enhanced Crosswalk Project. We recently approved the retention payment, so once we get a copy of the
check (or proof of payment to Contractor) we will submit a reimbursement request for this TDA grant. Only one reimbursement request package will be submitted.
East Valley grant: We are working to complete the reimbursement request #1 package in the amount of $99,391. This grant is used to fund the design portion of the ATP Cycle 3 East Valley
Corridor project and we are 75% done with the design – we should be done with the design early next year. In total, we will probably have 3 reimbursement request submitted to SBCTA.
Additionally, could you please update the contact list for the City? Please remove Chris Diggs and Savat Khamphou, as they are no longer with the City, and include Goutam Dobey, Gerard
Nepomuceno, Ross Wittman, and myself.
Please let me know if additional information is needed.
Thanks,
Veronica Medina, E.I.T.
Assistant Engineer
Municipal Utilities & Engineering Department
City of Redlands
Office: (909) 798-7584 ext. 6
From: Ginger Koblasz [mailto:gkoblasz@gosbcta.com]
Sent: Tuesday, October 27, 2020 5:23 PM
To: 'skhamphou@cityofredlands.org' <skhamphou@cityofredlands.org>; 'cdiggs@cityofredlands.org' <cdiggs@cityofredlands.org>; Gerard Nepomuceno <gnepomuceno@cityofredlands.org>; Ross Wittman
<rwittman@cityofredlands.org>
Subject: TDA Article 3 Grant Time Extension Letter
Team Redlands,
Attached is a summary of the City of Redlands’ active TDA Article 3 awards. Can someone please let me know what the status is for the two awards that expired in 2019?
Thanks,
Ginger
From: Ginger Koblasz
Sent: Tuesday, September 29, 2020 3:06 PM
To: 'gnepomuceno@cityofredlands.org'
Cc: Michele Fogerson; Josh Lee
Subject: FW: TDA Article 3 Grant Time Extension Letter
Hi Gerard,
Unfortunately SBCTA staff is only authorized to grant two one year extensions on TDA Article 3 projects. I’ll look into getting this item added to the Board agenda.
Regards,
Ginger Koblasz
Senior Planner
1170 West Third Street, 2nd Floor
San Bernardino, CA 92410
909.884.8276 | Office
From: Gerard Nepomuceno [mailto:gnepomuceno@cityofredlands.org]
Sent: Tuesday, September 29, 2020 1:37 PM
To: Josh Lee <jlee@gosbcta.com>
Subject: TDA Article 3 Grant Time Extension Letter
Hello Mr. Lee,
I have attached a letter requesting an extension on the TDA Article 3 grant for the Orange Blossom Trail Phase 3 project in the City of Redlands. I will also be sending you physical
copy through the mail by the end of the week. Please let me know if you have any questions regarding this request.
Thank you,
Gerard Nepomuceno E.I.T.
City of Redlands
Associate Engineer
Municipal Utilities & Engineering Department
35 Cajon Street, Suite 15A Redlands, CA 92373
(909) 798-7584 ext. 4