RE: FY17/18 Bike & Ped Route Maintenance AB Miller High School – Extension
Dear Reynolds:
This letter serves as a response to your communication on 10/21/20 granting the City of Fontana a
deadline extension to complete the San Bernardino County Transportation Authority (SBCTA) Board of
Directors approved Transportation Development Act (TDA) Article 3 grant funded project as outlined
below.
Project Type Bicycle/Pedestrian
Allocation Number L18-0702-0737-01
Project Description Bike & Ped Route Maintenance AB Miller High School
TDA Article 3 Award $50,000
Local Match $112,000
Local Share 69.1%
ATP Share (if applicable) NA
Total Project Cost $162,000
Original Deadline 11/30/2019
Revised Deadline 11/30/2021
Extension Number* 2
*As long as the project is progressing, SBCTA staff has the authority to grant two one
year extensions. Additional extension(s) must be approved by the SBCTA Board.
As a friendly reminder, the TDA Article 3 grant award is paid through a reimbursement process upon
project completion. It is required that a TDA claim form and supporting documentation of project
completion submitted to SBCTA prior to disbursement of funds. The TDA Article 3 grant award is for a
maximum reimbursable amount. Should your project exceed the maximum reimbursable amount, SBCTA
will not provide any additional reimbursement. For projects completed under the awarded amount,
SBCTA will reimburse your agency for the TDA Article 3 share of the project using the match percentage
identified above and in your grant application. Please also keep in mind that staff expenses may not be
used to fulfill the local match requirement.
Upon project completion, please contact me for the TDA Claim Form and filing instructions.