Dear Ms. Jaiswal:
This letter serves as a response to the Omnitrans’ request to extend the period of time to complete projects
for the Transit Stop Access Program of Transportation Development Act (TDA) Article 3 and to amend
the scope for another project. In Fiscal Year 2016/17, the San Bernardino County Transportation
Authority (SBCTA) Board of Directors approved grant awards to various bus stop projects operated by
Omnitrans. In total, $273,351 was award to 21 bus stops. One of these stops was for Barton and
Terracina, in the City of Redlands, which includes funding of $10,001. SBCTA concurs with the request
to extend the period of time to complete all bus stop projects for this award. The revised project
completion date for this project is December 31, 2021. SBCTA also concurs with request to change the
project scope to use the TDA Article 3 funds at Barton and Terracina towards five new locations within
the City of Redlands which include:
Citrus at Dearborn WB
Citrus at Dearborn EB
Lugonia at University WB
Lugonia at Grove WB
Alabama at Storage Dr SB
As a friendly reminder, the TDA Article 3 grant award is paid through a reimbursement process upon
completion of the project. It is required that a TDA claim form and supporting documentation of project
completion are submitted to SBCTA prior to disbursement of funds to Omnitrans. The TDA Article 3
grant award is for a maximum reimbursable amount. Should your project exceed the maximum
reimbursable amount, SBCTA will not provide any additional reimbursement. For projects completed
under the awarded amount, SBCTA will reimburse your agency for the TDA Article 3 share of the project
using the match percentage identified in your grant applications.
Upon completion of the projects, please contact Nancy Stricker, Transportation Programming Analyst, at
SBCTA for the TDA Claim Form and filing instructions for the Bicycle/Pedestrian project.. Vanessa can
be reached at (909) 884-8276 or nstrickert@gosbcta.com. Should you need additional information
regarding this matter, please contact Cameron Brown, Senior Planner, at (909) 884-8276 or
cbrown@gosbcta.com.