Art3_Redlands_2024 Active Projects StatusHi Lisa,
Please see updated table below reflecting project updates. Please let me know if you have any questions/comments.
Thanks,
Veronica Medina, E.I.T.
Associate Engineer
Municipal Utilities & Engineering Department
City of Redlands
Office: (909) 798-7584 ext. 6
From: Lisa Chou <lchou@gosbcta.com <mailto:lchou@gosbcta.com> >
Sent: Monday, August 5, 2024 6:22 PM
To: MUED User <mutilities@cityofredlands.org <mailto:mutilities@cityofredlands.org> >
Cc: Ginger Koblasz <gkoblasz@gosbcta.com <mailto:gkoblasz@gosbcta.com> >; Nancy Strickert <nstrickert@gosbcta.com <mailto:nstrickert@gosbcta.com> >
Subject: TDA Article 3 Annual Report - Redlands
You don't often get email from lchou@gosbcta.com <mailto:lchou@gosbcta.com> . Learn why this is important <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Faka.ms%2FLearnAboutSenderIdentificat
ion&data=eJxNjLsKwkAQAL8mVwbzMNhckUZQxEK_YHO7iUdyu3K7EczXm1KYYmBggu-qsa1CS6eqq9Ghn0SHYFAGSS75qP3W3B_r8crq1H8SYWQo2kOI9pUxEy7AqKXkyWU_zTIsoNve_zerf5m9tWj6oj7vwAxl0l1uBJn7QVZ7EiPlCxJbHGMAi8I_M0Y2dw%%>
[NOTICE: This message originated outside of City of Redlands -- DO NOT CLICK on links or open attachments unless you are sure the content is safe.]
Good afternoon,
I’m a contract planner assisting Ginger Koblasz on the TDA Article 3 annual progress report. Could you please provide an update on Redlands’s active Transportation Development Act (TDA)
Article 3 awards?
Award Fiscal Year
Description
Project Type
Project Total
TDA Article 3 Award
TDA Article 3 Distribution To-Date
Local Share Total
Deadline
Status
Estimate of Expenses to Date
Contractor Selected
(yes or no)
Able to Complete by Deadline
(yes or no)
2021/2022
Transit Stops Improvements in the City of Redlands
Transit
$46,340.00
$46,340.00
$0.00
$0.00
2025-06-30
Contract award for construction is waiting City Council approval. Construction for all 10 project locations is anticipated to begin September 9, 2024.
$0.00
Yes
Yes
2023/2024
Orange Blossom Trail Phase IV
Bike/Ped
$1,282,000.00
$1,089,700.00
$0.00
$192,300.00
2027-06-30
The plans are currently under second review with SBCFCD. Once permit is obtained, the project will be advertised for construction.
$2,000.00
No
Yes
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any potential issues and limit the number
of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting requirement, awardees must also demonstrate expenditure of some funds
within ONE year of award notification and, for construction contracts, a contract must be awarded within THREE years of award notification. We expect there to be some leniency for existing
awards, particularly with the one year expenditure rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete the project
by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Fwww.gosbcta.com%2Fwp-content%2Fuploads%2F2022%2F12%2F2023-05-03-
Board-of-Directors-Full-Agenda-1928.pdf%23page%3D298&data=eJxNjM2KwyAUhZ_G7G6I1zSkCxct6Q_MQxSrxoTaXFHTMH36OsymcOD8fHC07PjYct3anndoKiMdpbvOqtb0rJ7ydB1ul93Pq_u9YZXkS0-0srbR07zQNHufaoquitI96O5Vehf2fbDKK
eeQmDgwPBdt21Z_8b8lgKYl2yWXsgZPyqSSsEEsxvE_C2h20Ag4kooGaIRhjlZnignOq_dwcHYxCvge-zqYkaEIylkmBtz3HxD7SKQ%25> or feel free to reach out to me directly with questions.
Thank you,
Lisa Chou, AICP
San Bernardino County Transportation Authority
Contract Planner
1170 West Third Street, 2nd Floor
San Bernardino, CA 92410
Office: 626.204.9801 Cell: 626.630.6127
The information in this e-mail and any attachments are for the sole use of the intended recipient and may contain privileged and confidential information. If you are not the intended
recipient, any use, disclosure, copying or distribution of this message or attachment is strictly prohibited. If you believe that you have received this e-mail in error, please contact
the sender immediately and delete the e-mail and all of its attachments.
________________________________
This message contains confidential information and is intended only for the individual(s) addressed in the message. If you are not the named addressee, you should not disseminate, distribute,
or copy this e-mail. If you are not the intended recipient, you are notified that disclosing, distributing, or copying this e-mail is strictly prohibited.
ded recipient, any use, disclosure, copying or distribution of this message or attachment is strictly prohibited. If you believe that you have received this e-mail in error, please contact
the sender immediately and delete the e-mail and all of its attachments.
ct: TDA Article 3 Annual Report - Fontana
CAUTION - EXTERNAL SENDER - THIS EMAIL ORIGINATED OUTSIDE OF THE CITY'S EMAIL SYSTEM
Do not click links or open attachments unless you recognize the sender and know the content is safe.
Good afternoon,
Could you please provide an update on Fontana’s active Transportation Development Act (TDA) Article 3 awards?
Award Fiscal Year
Description
Project Type
Project Total
TDA Article 3 Award
TDA Article 3 Distribution To-Date
Local Share Total
Deadline
Status
Estimate of Expenses to Date
Contractor Selected
(yes or no)
Able to Complete by Deadline
(yes or no)
2017/2018
Alder Middle School SRTS
Bike/Ped
$503,036.00
$250,000.00
$132,847.70
$253,036.00
2024-12-31
2021/2022
Transit Stops Improvements in the City of Fontana
Transit
$75,160.00
$37,580.00
$0.00
$37,580.00
2025-06-30
2023/2024
Rectangular Rapid Flashing Beacons (x7 - reduced to "3-4")
Bike/Ped
$70,000.00
$52,500.00
$0.00
$17,500.00
2027-06-30
2023/2024
Catawba SRTS Sidewalk
Bike/Ped
$792,697.00
$396,348.00
$0.00
$396,349.00
2027-06-30
2023/2024
10 Bus Pads in the City of Fontana
Transit
$84,319.00
$59,023.00
$0.00
$25,296.00
2027-06-30
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any potential issues and limit the number
of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting requirement, awardees must also demonstrate expenditure of some funds
within ONE year of award notification and, for construction contracts, a contract must be awarded within THREE years of award notification. We expect there to be some leniency for existing
awards, particularly with the one year expenditure rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete the project
by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Fwww.gosbcta.com%2Fwp-content%2Fuploads%2F2022%2F12%2F2023-05-03-
Board-of-Directors-Full-Agenda-1928.pdf%23page%3D298&data=eJxNjM2KwyAUhZ_G7G6I1zSkCxct6Q_MԐᔀᩃU聀辔ƃ