Art3_Ontario_2024_Active Projects StatusHi Lisa,
I populated the table in red below.
We plan on constructing both TDA projects with an upcoming traffic signal project that will award before the end of 2024. Improvement plans are currently in review. We have not expended
any funds yet as the TDA funds are programmed for construction.
Please let me know if you need additional information. Thanks!
Jay Bautista, P.E., T.E.
Traffic/Transportation Manager
City of Ontario
303 East B Street
Ontario, CA 91764
(909) 395-2120
jbautista@ontarioca.gov <mailto:jbautista@ontarioca.gov>
From: Khoi Do
Sent: Tuesday, August 06, 2024 8:18 AM
To: Jay Bautista <JBautista@ontarioca.gov>
Subject: FW: TDA Article 3 Annual Report - Ontario
Good morning Jay.
Could you follow-up? Thx.
From: Lisa Chou <lchou@gosbcta.com <mailto:lchou@gosbcta.com> >
Sent: Monday, August 5, 2024 6:13 PM
To: Khoi Do <KDo@ontarioca.gov <mailto:KDo@ontarioca.gov> >
Cc: Ginger Koblasz <gkoblasz@gosbcta.com <mailto:gkoblasz@gosbcta.com> >; Nancy Strickert <nstrickert@gosbcta.com <mailto:nstrickert@gosbcta.com> >
Subject: TDA Article 3 Annual Report - Ontario
Good afternoon,
I’m a contract planner assisting Ginger Koblasz on the TDA Article 3 annual progress report. Could you please provide an update on Ontario’s active Transportation Development Act (TDA)
Article 3 awards?
Award Fiscal Year
Description
Project Type
Project Total
TDA Article 3 Award
TDA Article 3 Distribution To-Date
Local Share Total
Deadline
Status
Estimate of Expenses to Date
Contractor Selected
(yes or no)
Able to Complete by Deadline
(yes or no)
2021/2022
Bus Stop Pad Installation Project
Transit
$67,049.89
$67,049.89
$0.00
$0.00
2025-06-30
Completing design
$0
no
yes
2023/2024
Ontario Improvements - 3 Stops
Transit
$32,835.00
$32,835.00
$0.00
$0.00
2027-06-30
Completing design
$0
no
yes
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any potential issues and limit the number
of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting requirement, awardees must also demonstrate expenditure of some funds
within ONE year of award notification and, for construction contracts, a contract must be awarded within THREE years of award notification. We expect there to be some leniency for existing
awards, particularly with the one year expenditure rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete the project
by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) [linklock.titanhq.com] <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Furldefense.com%2Fv3%2F__https%3A%2Flinklo
ck.titanhq.com%2Fanalyse%3Furl%3Dhttps%2A3A%2A2F%2A2Fwww.gosbcta.com%2A2Fwp-content%2A2Fuploads%2A2F2022%2A2F12%2A2F2023-05-03-Board-of-Directors-Full-Agenda-1928.pdf%2A23page%2A3D298%26data%3DeJxNjM
2KwyAUhZ_G7G6I1zSkCxct6Q_MQxSrxoTaXFHTMH36OsymcOD8fHC07PjYct3anndoKiMdpbvOqtb0rJ7ydB1ul93Pq_u9YZXkS0-0srbR07zQNHufaoquitI96O5Vehf2fbDKKeeQmDgwPBdt21Z_8b8lgKYl2yWXsgZPyqSSsEEsxvE_C2h20Ag4kooGaIRhjlZni
gnOq_dwcHYxCvge-zqYkaEIylkmBtz3HxD7SKQ%2A25__%3BJSUlJSUlJSUlJSU%21%21NvlOg7bCjmerYEY%21Um4PxFx71wlQs76mMKSFgah5IdpMVg6Lit8XF3yh3v5erR-fl9cJFppqlkQIVxgPKDCEtjc9Wev289U%24&data=eJxNUNmSqkAM_Rp8w4JuZXnw
AUVG5boNs6gvVNM0DdLQLM3m11-cubfKqiSVnOScpIIXmhrNVDwjhqqBcBIuKK8DLNAU82ySLR7xLMGOwAfLMif14h6gRiS1QNJM4blAVcIxmlLeTqoFTXnAUP0YW68azSIWoqglaEnAGa2pWEgiktfk2R6BFo7B91-mWJKnjON0KhKB8rj8N4hyxIaaSPCpIUH7lwG
sJ8d6ao-h67rpy_ZfrJDxeCzJxU_ZFIyjsP7JgQLAT6KC_zWUlbmsQHnJURXKPJLtpCJY8KqWnYYx2aIkD5GsmsCYFmH0pMECUfI8xAamIQEtROODoE12_eG-B243WJ_xzX_T37St-vDSVY-Fdvb3596rev6BLs7mY7-B2rEeMny0jWizUvTT_YoFRHkecjfZh0XQHk
sRKNVOH8Kl2jATnkq_Ma-3S-opslJXwbuiP86HTRMhXjaJ2Jracf5F4ghEge26hJwzm3anZSiAevONwGDUvTIwfF9qejsNpefV63Xdt2t_BWKgWHSWcv6Gtu_xnd3yhObH0g87vLn2q5YS-VFeU7TeDizNluIBN72te-75-Y2570twufM-2YtLQB3t0LIj1YPVPSPVd
X0dkc9sduqdXlc7dq51Ldu7nkNRPN-Gxf6Lan8SYVwcOMSwnZPqXY6YiXdOUZQsPW-_enpy7dVa3LH5TVpgmOOa2V9LFu0P> or feel free to reach out to me directly with questions.
Thank you,
Lisa Chou, AICP
San Bernardino County Transportation Authority
Contract Planner
1170 West Third Street, 2nd Floor
San Bernardino, CA 92410
Office: 626.204.9801 Cell: 626.630.6127
The information in this e-mail and any attachments are for the sole use of the intended recipient and may contain privileged and confidential information. If you are not the intended
recipient, any use, disclosure, copying or distribution of this message or attachment is strictly prohibited. If you believe that you have received this e-mail in error, please contact
the sender immediately and delete the e-mail and all of its attachments.
ct: TDA Article 3 Annual Report - Fontana
CAUTION - EXTERNAL SENDER - THIS EMAIL ORIGINATED OUTSIDE OF THE CITY'S EMAIL SYSTEM
Do not click links or open attachments unless you recognize the sender and know the content is safe.
Good afternoon,
Could you please provide an update on Fontana’s active Transportation Development Act (TDA) Article 3 awards?
Award Fiscal Year
Description
Project Type
Project Total
TDA Article 3 Award
TDA Article 3 Distribution To-Date
Local Share Total
Deadline
Status
Estimate of Expenses to Date
Contractor Selected
(yes or no)
Able to Complete by Deadline
(yes or no)
2017/2018
Alder Middle School SRTS
Bike/Ped
$503,036.00
$250,000.00
$132,847.70
$253,036.00
2024-12-31
2021/2022
Transit Stops Improvements in the City of Fontana
Transit
$75,160.00
$37,580.00
$0.00
$37,580.00
2025-06-30
2023/2024
Rectangular Rapid Flashing Beacons (x7 - reduced to "3-4")
Bike/Ped
$70,000.00
$52,500.00
$0.00
$17,500.00
2027-06-30
2023/2024
Catawba SRTS Sidewalk
Bike/Ped
$792,697.00
$396,348.00
$0.00
$396,349.00
2027-06-30
2023/2024
10 Bus Pads in the City of Fontana
Transit
$84,319.00
$59,023.00
$0.00
$25,296.00
2027-06-30
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any potential issues and limit the number
of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting requirement, awardees must also demonstrate expenditure of some funds
within ONE year of award notification and, for construction contracts, a contract must be awarded within THREE years of award notification. We expect there to be some leniency for existing
awards, particularly with the one year expenditure rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete the project
by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Fwww.gosbcta.com%2Fwp-content%2Fuploads%2F2022%2F12%2F2023-05-03-
Board-of-Directors-Full-Agenda-1928.pdf%23page%3D298&data=eJxNjM2KwyAUhZ_G7G6I1zSkCxct6Q_MԐᔀᩃU聀辔ƃ