Art3_Twentynine Palms_2024 Active Projects StatusLet me know if you need anything else.
Rich
On Tue, Aug 6, 2024 at 3:00 PM Richard Pedersen <richardpedersen@caa.inc> wrote:
HI Rich,
Could you respond to Ginger regarding the Channel Trail Class 1 Project, please. If you need anything from me let me know.
Richard
On Aug 6, 2024, at 7:17 AM, Keith Gardner <kgardner@29palms.org <mailto:kgardner@29palms.org> > wrote:
Can you assist on this response?
From: Lisa Chou <lchou@gosbcta.com <mailto:lchou@gosbcta.com> >
Sent: Monday, August 5, 2024 6:54 PM
To: Keith Gardner <kgardner@29palms.org <mailto:kgardner@29palms.org> >
Cc: Ginger Koblasz <gkoblasz@gosbcta.com <mailto:gkoblasz@gosbcta.com> >
Subject: TDA Article 3 Annual Report - Twentynine Palms
CAUTION: THIS EMAIL ORIGINATED OUTSIDE THE ORGANIZATION. DO NOT CLICK LINKS OR OPEN ATTACHMENTS UNLESS YOU HAVE VERIFIED THE SENDER AND KNOW THE CONTENT IS SAFE. CAUTION
Good afternoon,
I’m a contract planner assisting Ginger Koblasz on the TDA Article 3 annual progress report. Could you please provide an update on Twentynine Palms’ active Transportation Development
Act (TDA) Article 3 awards?
Award Fiscal Year
Description
Project Type
Project Total
TDA Article 3 Award
TDA Article 3 Distribution To-Date
Local Share Total
Deadline
Status
Estimate of Expenses to Date
Contractor Selected
(yes or no)
Able to Complete by Deadline
(yes or no)
2023/2024
Channel Trail Class I
Bike/Ped
$495,000.00
$420,750.00
$0.00
$74,250.00
2027-06-30
On May 3, 2023, the SBCTA Board approved changes to the program that now require annual Progress Reports. We hope this will help us get ahead of any potential issues and limit the
number of times we need to go to the Board with scope change and extension requests. In addition to the progress reporting requirement, awardees must also demonstrate expenditure of
some funds within ONE year of award notification and, for construction contracts, a contract must be awarded within THREE years of award notification. We expect there to be some leniency
for existing awards, particularly with the one year expenditure rule. If funds have not yet been spent, please provide a brief project schedule showing how the City intends to complete
the project by the deadline.
For more information please see: Agenda - Wednesday, May 3, 2023 (gosbcta.com) <https://linklock.titanhq.com/analyse?url=https%3A%2F%2Fwww.gosbcta.com%2Fwp-content%2Fuploads%2F2022%2F12%2F2023-05-0
3-Board-of-Directors-Full-Agenda-1928.pdf%23page%3D298&data=eJxNjM2KwyAUhZ_G7G6I1zSkCxct6Q_MQxSrxoTaXFHTMH36OsymcOD8fHC07PjYct3anndoKiMdpbvOqtb0rJ7ydB1ul93Pq_u9YZXkS0-0srbR07zQNHufaoquitI96O5Vehf2fbD
KKeeQmDgwPBdt21Z_8b8lgKYl2yWXsgZPyqSSsEEsxvE_C2h20Ag4kooGaIRhjlZnignOq_dwcHYxCvge-zqYkaEIylkmBtz3HxD7SKQ%25> or feel free to reach out to me directly with questions.
Thank you,
Lisa Chou, AICP
San Bernardino County Transportation Authority
Contract Planner
1170 West Third Street, 2nd Floor
San Bernardino, CA 92410
Office: 626.204.9801 Cell: 626.630.6127
The information in this e-mail and any attachments are for the sole use of the intended recipient and may contain privileged and confidential information. If you are not the intended
recipient, any use, disclosure, copying or distribution of this message or attachment is strictly prohibited. If you believe that you have received this e-mail in error, please contact
the sender immediately and delete the e-mail and all of its attachments.
--
Rich Berger
Project Manager
Charles Abbott Associates, Inc.
760-617-0310