Art3_SanBernardino_FY19_Transit_Accessibility_ScopeRqst_231211
Office: 201 North “E” Street, 2nd Floor
290 North D St, San Bernardino, CA 92401 | P: 909-384-5140 | www.SBCity.org
Public Works Department
TDA Article 3 Grant, FY 19 - L20-SB-14 $26,936
Bus Stop Improvements
Notice of Scope Change
December 11, 2023
Attn: SBCTA
Change of Specifications:
The City wants to omit the following bus stops:
5622: 5th St @ J street
60: Sierra Way @ Ralston Ave
The following stops were completed on 3/23/2021:
5691: Base Line St @ Sepulveda Ave
54: 9th St @ Medical Center Dr
Explanations:
1. The City of San Bernardino finished the project within the original �meframe, however
because the person(s) being in charge of this project le� their employment with the city,
the reimbursement claims were not filed on �me.
2. A scope change is requested, since the grant funds were not enough to do the
construc�on work on four bus stops. Only two out of four loca�ons were done at a much
higher cost than the total grant fund.
3. Emails from SBCTA were not responded/followed up, due to employees that were
handling the project(s) leaving their employment with the City.
4. Same reason as No.3 above applies to the no�ces of recission not being responded in a
�mely manner.
Sincerely,
David Marghezi
Public Works Engineering